Seeking as ever to optimize scheduling, owners
often voyage charter out while a vessel is still performing a previous fixture,
and will sometimes enter into an intermediate charter, which they plan to complete
beforehand.
Charterers’ and often sellers’ arrangements depend
on valid arrival or loading dates, and owners must ensure that all such are
genuine and reasonable. In giving them, they must allow for transit, cargo
operations and all ancillary matters, and will sometimes be held to account
under familiar provisions and well established principles.
Thus:
1) If a fixture says that owners will proceed with
all convenient speed or, often, with the utmost dispatch to a load port, and
also gives an ETA or ERTL ("Expected
Ready To Load") , owners have an absolute obligation to start the approach voyage
at a time when it is reasonably certain that the vessel will arrive on or around
the given date;
2) Any charter party exceptions only apply once the
approach voyage has begun. A vessel might be delayed, in port or transit, for many
reasons, including congestion, bad weather, breakdown or even casualty. Which
side bears the risk of operational difficulty depends on what has been
promised, or excluded, by the fixture wording. MOL’s VLCC ‘Pacific Voyager’ is
a good example of that.
Still laden under a prior charter party, the
vessel was fixed on an amended Shellvoy5 form for carriage to the Far East and
had to “perform her service with utmost dispatch and ... proceed to [Rotterdam]
… and ... load ... “.
This fixture had no load port ETA or ERTL, but (by
incorporating the previous charter itinerary for the Red Sea, eastern
Mediterranean and English Channel) it gave an ETA at that final disport, near Le
Havre.
During the Suez Canal transit and through no fault
of owners, the vessel hit a submerged object.
She needed extensive repairs and charterers terminated
and sought damages. Subject to liability, these were agreed at $1.2 mill.
Before this decision, it was unclear whether the
absolute obligation at (1) above in fact arose where no load port ETA or ERTL had
been given. So the question was whether, in those circumstances, such
nevertheless existed, and by reference to (a) the previous itinerary or perhaps
(b) the cancelling date.
It was agreed that (2) above meant that owners could
not invoke any charter party exception.
Trial
The trial Judge ruled that the various ETAs under
the prior fixture equated to estimates on which charterers could rely in
identifying the commencement of their chartered service, and in order to make
loading arrangements, and were thus meant to perform the same function as a load
port ETA.
Owners were therefore under an absolute obligation
to start the approach voyage to Rotterdam after a reasonable time for
discharging at her final disport under the previous fixture.
Owners argued that:
(a) Wording that differed from that in the decided
cases meant a different outcome - here there was no load port ETA or ERTL, and
the utmost despatch obligation was expressly ‘subject to the terms of this charter’,
so
(b) Such could only arise when the vessel left the
final disport under her prior charter; but
(c) It never arose, as that never happened (charterers
countered that, if this was right, the utmost despatch obligation would not apply
even if failure to leave the last disport had been entirely owners’ fault);
(d) Just as for the common shorthand ‘bss iagw/ wp’,
the itinerary was simply to highlight that the vessel was still performing
under a prior charter party.
The Court of Appeal ruled that:
1) The itinerary was very important to charterers,
and did not merely signpost that the vessel was still subject to a previous charter;
2) Nor did ‘bss iagw/wp’, which instead emphasized
that (as anyway required) the estimates were honest and on reasonable grounds,
and owners got no help from ‘subject to the provisions of this charter’;
3) Likewise, the utmost despatch obligation is
important and is intended to assist a charterer. The prior itinerary plainly
showed that the vessel was not to sail for the load port ‘forthwith’, and it
could also be used to determine the alternative obligation, which was to start
that approach voyage when the vessel would reasonably be supposed to have left
her last disport after a reasonable time for discharging.
Owners were therefore in breach of their obligation,
since they did not sail for Rotterdam, then or at any time, and were liable for
$1.2 mill.
C Demurrage commented - This decision shows that,
even if there is no ETA or ETRL, if owners want to make the beginning of a
charter service contingent on the conclusion of the prior one, very clear words
will be needed.
In another case analyzed by C Demurrage,
the question of an arbitration agreement arose again.
This familiar issue arose in a novel way in Sonact
Group Ltd v Premuda SpA (the ‘FOUR ISLAND’) ([2018] EWHC 3820 (Comm)).
Most fixtures contain clauses that make disputes
subject to, say, English law and High Court jurisdiction, or more often provide
for arbitration, also detailing how the tribunal is formed and citing the
governing rules, such as LMAA.
But very few demurrage disputes get that far.
Commercial operators document, present, negotiate and settle in the great
majority of cases.
This is mostly undertaken by correspondence but occasionally
at a meeting, called to wrangle over a number of matters, with each side
generally seeking one overall deal. Sometimes lawyers are involved, but even
then the bargain is typically recorded just by email. Formal documents are
sometimes drawn up, but
not usually.
An awkward problem?
But what if charterers do not pay the agreed
sum? Owners will press them, perhaps then involving lawyers, but in most cases
the only way to compel payment is by formal action. But that cannot be under the charter party.
It has to be under the settlement agreement that (for this purpose) has replaced
it.
However, while the fixture may have stipulated arbitration
in the clearest terms, the concluding deal may not have done, and that might
enable charterers to challenge owners’ attempted arbitration, by urging lack of
jurisdiction.
That is exactly what happened in the Aframax ‘Four Island’
case. Owners Premuda claimed almost $719,000 demurrage and about $190,000
heating costs under an amended Asbatankvoy charter that contained the usual
arbitration clause.
The claim was settled by an email exchange, under which
charterers Sonact Group agreed to pay $600,000 for all owners’ claims.
But they did not pay, and later challenged arbitration on
the basis that the agreement did not provide for that, so the arbitrators had
no jurisdiction over a claim for the agreed sum.
They said that owners’ claim was not under the charter party.
It was under the settlement agreement. That did not have an arbitration provision
and no words had been used that could incorporate the charter party clause.
The Tribunal ruled that it did have jurisdiction, as there
was an agreement to arbitrate anything arising under the settlement, and on
appeal the
Judge agreed.
The Judge said that:
1. As mostly happens, the parties had traded views, in
writing, and eventually reached an agreement;
2. That was likewise in correspondence, and not in a
separate, self-contained document;
3. The parties’ unstated intention was that their agreement
should have the same dispute resolution wording as the fixture under which the
claims arose;
4. Claims handling like this is standard, and parties would
be astonished to be told that the same mechanism did not apply;
5. Anything else would require the payee to establish court
jurisdiction, probably where the defaulting party was based;
6. Parties can agree dispute resolution terms that differ
from their charter party; however
7. Especially if there is no separate settlement agreement,
but just an exchange of emails, any such would have to be expressly recorded,
and could not simply be inferred;
8. It was obvious that the parties intended the arbitration
clause to continue to apply if the settlement sum was not paid, and inconceivable
that they had contemplated anything else;
9. There was no rule that, once parties enter into the new
legal relationship of a settlement agreement, an arbitration clause in the underlying
contract no longer applies; It was equally obvious that the parties intended that
English law, as in the charter party, would likewise still apply.
Charterers also argued that, under owners’ notice commencing
arbitration, the arbitrators had been appointed for disputes under the charter
party not the settlement agreement.
The Judge rejected that, too. Applying the established
“broad and flexible approach”, the notice here was effective to refer a claim
for the agreed sum to arbitration.
Discussion
Charterers’ arguments were firmly rejected, but the Court
did not lay down a general rule, and each case is different.
Where, as normal, a demurrage claim is made and settled in
correspondence, it might be hard for a defaulter to argue that the charter
party dispute resolution terms no longer apply.
But that will not always be so. It will depend on what the
parties have said, and the exchanges might allow one side to argue that some
other mechanism applies to the settlement.
This is perhaps especially so where the parties have
captured their agreement in a separate document, or maybe under a different
string of correspondence.
It may also be so where the parties have met to deal in
aggregate with several claims, arising under fixtures with different disputes
clauses, so it may be hard to say which was intended to apply.
Parties should take great care, and perhaps seek advice on
this. It will generally be sensible to ensure that a settlement agreement, in
whatever form, deals expressly with how any dispute under it will be
determined, C Demurrage said.
Δεν υπάρχουν σχόλια:
Δημοσίευση σχολίου