The use of mass flow
meters (MFM) is mandatory for all fuel oil deliveries in Singapore, as of 1
January 2017. However, issues related to bunker quantity remain prevalent,
according to Gard P&I Club. In this context, the Club presents some
issues faced by operators, when taking bunkers in Singapore, following the
implementation of the MFM requirements.
The introduction of mandatory use of MFMs was intended to
address frequent quantity disputes arising between the bunker barge and the
receiving vessel, although these issues remain.
Causes
·
Operational
practices by the bunker barge operators
Gard has received reports indicating that some bunker barges
were found to syphon fuel back to their tanks via pipe connections between the
flow meter and the outlet flange going to the ship manifold. In such
circumstances, the MFM reading will be higher than the amount actually received
by the ship’s bunker tanks.
The Maritime Port Authority of Singapore is currently
investigating these issues and has suspended several barges from operations
until completion of the investigation. It is worth noting that an MPA certified
bunker barge should have all connections between the flow meter and the
shipside blanked off and sealed as part of the certification.
·
Limitations
of the equipment itself.
Some vessels have recently reported quantity difference
exceeding their past experience. Some bunker surveyors have studies the
discrepancy between the MFM readings and the vessel received figures for a
duration of time. Out of 24 cases of discrepancies over the duration, the
maximum discrepancy was 57.24 MT and minimum 6.79 MT. The average discrepancy,
in the disputed cases, was approximately 19 MT.
These discrepancies can be due to:
·
Errors
in the tank calibration tables for the receiving vessel.
·
Errors
in the MFM’s measurement of the flow rate.
·
Any
errors in the tank calibration of the vessel would be consistent with or
without the MFM. To identify this issue a vessel experience factor (VEF) from
her previous bunkering operations should be taken into account.
Errors in the MFM reading can also account for such
discrepancies. All MFMs have a maximum and minimum flow rate, commonly known as
“Qmax” and “Qmin” respectively. As Gard explains, these limits define the
operational accuracy within which the system is qualified to operate. This
means that, if the flow rate of the liquid is outside these limits, the
calibration of the equipment may not be accurate.
Moreover, the accuracy of measurement can be influenced by MFM
parameters such as Damping, Drive Gain, Low Flow Cut Off Value & Air Index,
if they exceed the manufacturers’ recommended limits during the bunkering
operation.
While stripping of the bunker tanks is allowed under the TR48
(Technical Reference For Bunker Mass Flow Metering), it has been noted that
prolonged stripping operations causes frequent fluctuations in the flow rate
with several instances of the flow rate falling below the Qmin. It has also
been observed that some bunker barges conduct stripping operations in the
middle of bunkering which is not permitted under TR48 and can lead to measurement
uncertainty.
Recommendations
1. Compare
the certificate of the MFM with the actual equipment fitted on the barge
(comparing the serial number) to verify that the certificate is for the
equipment actually fitted.
2. Seal
checks: there are a number of seals, up to 20 in some cases, fitted on the MFM
and other piping on the barge. These seals have to be checked and verified
before every delivery.
3. The
bunker surveyors should inspect the barge piping, especially around the
manifold areas for any drain lines, fittings or stub pieces from where bunker
oil may be tapped back into the barge tanks. If any such fittings are found,
the surveyors are instructed to seal any valves leading to such fittings and
report the vessel’s chief engineer to the Maritime Port Authority of Singapore.
The surveyor should also ensure that the Meter Totalizer Log is available for
inspection as required under TR48.
4. Meter
Zero should be the last thing that is done before commencing the bunker delivery
and must always be done AFTER the hose has been fitted to the ship’s manifold.
5. Where
the bunker surveyor has been engaged, the survey report should indicate an
evaluation of the meter profile in order to ensure that the basic MFM profile
parameters (Qmin, Damping, Drive Gain, Low Flow Cut Off Value & Air Index)
are within operating limits.
If there is significant discrepancy between the vessel received
figures and the MFM figures after having physically verified all the above
points, the following actions are recommended:
1. Repeat
steps 2 and 3
2. Inform
the MPA following the guidelines on “Mass Flow Meter Dispute Management”
3. Engage an MFM advisor to study
the meter profile in detail. This will involve the MFM profile ASCII files,
Transmitter Configuration Report etc. The surveyor should also be asked to
provide an independent opinion on the validity of the delivered quantity.